BANGALORE TO WAIT TILL 2012


Printer friendly page With Banner | Without Banner
Friday, February 20, 2009
Ministry of Urban Development

Proposals for Metro Rail Projects

19:7 IST

The proposal from some of the State Governments for setting up of Metro Rail Projects has been received by the Ministry of Urban Development, Government of India. The details of the proposals received from some of the states and action taken thereon is as follows:-

Sl.No.

State

Project

Length (in km)

Cost (Rs . in crore)

Present Status

(I) NATIONAL CAPITAL REGION, DELHI

1.

Delhi

Delhi MRTS

Phase I

Shahdara-Rithala

Vishwavidyalaya-Central Secretariat

Indraprastha-Dwarka

Dwarka sub-city (Dwarka- Dwarka VI)

65.05

22.06

10.84

25.65

6.5

10571

Project was sanctioned on 12.11.1996 and has been fully commissioned and made operational.

2.

Delhi

Delhi MRTS

Phase II

Vishva VidyalayaJahangir Puri

Central Secretariat – Qutub Minar

ShahdaraDilshad Garden

Indraprastha – New Ashok Nagar

Yamuna Bank – Anand Vihar ISBT

Kirti NagarMundka

(along with operational link to Inderlok)

54.675

6.36

12.525

3.09

8.07

6.16

18.47

8605.36

Project was initially sanctioned on 30.3.2006 and revised sanction order issued on 7.3.2008 and work started.

Target/Completion date

Commissioned on 3.2.2009

(9 months ahead of schedule)

30.6.2010

Commissioned on 30.6.2008

(6 months ahead of schedule)

30.6.2009

31.12.2009

31.3.2010

3.

Delhi

Extension of Delhi Metro from Ambedkar Nagar in Delhi to Sushantlok (Gurgaon)

14.47

1581

The project was sanctioned on 4.12.2006. It is targeted for completion by 31.7.2010.

4.

Delhi

Extension of Delhi Metro from New Ashok Nagar in Delhi to NOIDA Sector-32

7.0

827

The project was sanctioned on 19.3.2008. It is targeted for completion by 30.6.2009.

5.

Delhi

High Speed Express Link from New Delhi Railway Station to IGI Airport

19.2

3076

The project was sanctioned on 17.5.2007 and is under implementation. It is targeted for completion in June, 2010.

6.

Delhi

Central Secretariat to Badarpur

20.16

4012

The project was sanctioned on 17.5.2007. It is targeted for completion in June, 2010.

7.

Delhi

Express link from IGI Airport to Dwarka Sector-21

3.50

793

Project has been sanctioned on 29.1.2009 and is targeted for completion by 30.9.2010.

8.

Delhi

Extension of Delhi Metro to Faridabad

13.875

2028

The approval of Government of National Capital Territory, Delhi (GNCTD) being 50% owner of Delhi Metro Rail Corporation (DMRC) is awaited. Government of Haryana has also been requested to submit Comprehensive Mobility Plan (CMP), improvement of city bus service, setting up of special purpose vehicle, etc.

9.

Delhi

Metro link from Jahangirpuri to Badli

3.425

520

Project proposal has been received from Delhi Metro Rail Corporation (DMRC) only on 16.2.2009.

(II) OTHER THAN NATIONAL CAPITAL REGION

10.

Karnataka

Bangalore Metro Rail Project

Extension of North- South Corridor of Bangalore Metro Rail Phase-I .

33

9.3

6395

1763

Project was sanctioned on 11.5.2006. Work has been started and targetted for completion by 30.9.2012.

The project was approved by Empowered Group of Ministers on 30.1.2009.

11.

West Bengal

East-West Metro corridor, Kolkata

13.77

4676

Project was sanctioned on 30.7.2008. Work has been started and targeted for completion 2014-15.

12.

Tamil Nadu

Chennai Metro Rail Project, Tamil Nadu

50

14600

Project was sanctioned on 18.2.2009. The project is scheduled to be completed in 2014-15.

13.

Kerala

Kochi Metro Rail Project, Kerala

25.3

2991.5

The Planning Commission after detailed examination decided that in the absence of specific funding and low population of Kochi, it is not in a position to support the project from GOI funds presently. As and when policy and funds are in place, Planning Commission would relook the proposal.

14.

Andhra Pradesh

Hyderabad Metro Rail Project, Andhra Pradesh

71.29

11814

The Empowered Committee has accorded 'in principle' approval on VGF of Rs 2362 .88 crore i.e. 20% of the total cost.

15.

Maharashtra

Viability Gap Funding (VGF) for Versova-Andheri-Ghatkopar Metro Corridor.

Viability Gap Funding (VGF) for Charkop Bandra Mankurd Metro Corridor.

11.07

31.87

2356

7660

The proposal could not be taken up under Scheme for Financial Support to PPP in Infrastructure (popularly known as Viability Gap Funding Scheme (VGF) of Ministry of Finance as the tendering process has been started by State Government before the guidelines for VGF Scheme were issued.

The Empowered Committee has accorded 'in principle' approval for VGF of Rs. 1532 crore i.e. 20% of the total cost of Rs. 7660 crore.

This information was given by the Minister of State in the Ministry of Urban Development, Shri Ajay Maken in Lok Sabha today, in a written reply to a question by Shri S. Ajaya Kumar and Shri Pannian Ravindran.